Friday, May 30, 2014

Reno@Geylang - Screeding and waterproofing






now that the screeding and waterproofing works are completed, it's time for tiling works! Can wait to see the bathrooms once it's done because we have chosen a super uber looking tile for the common bath.

Meanwhile we are still waiting for HDB's approval for the hacking of walls...slight hiccup here. Apparently the original HDB drawing was wrong and did not reflect the true size of the column in the store room (it was like so short in the drawing but in actual fact it's bloody long! triple the length!!!) and missing an RC stiffener which is situated in the middle of the new proposed entrance foyer. So we have to go back to the drawing board again to think of ways to solve the long column.